Jumeirah Bay X3 Office – HAO Contracting
HAO case study

Jumeirah Bay X3 Office

A vacant shell-and-core half floor on Sheikh Zayed Road turned into a modern, clean, fully working Grade-A head office.

Case study · visualisations of the proposed works
Location
Cluster X, Jumeirah Lake Towers, Dubai
Type
Office fit-out · shell & core
Size
5,440 sq ft half floor · about 40 people
Programme
18–24 weeks
The property today

Five connected units on five title deeds, handed over as shell and core: bare screed, exposed services, floor-to-ceiling glazing along the full elevation and five drainage points that let the layout follow the occupier.

The brief: A modern, clean, fully working head office for about 40 people: reception, 38 desks plus a 20-seat co-working café, CEO and two manager offices, a 14-seat boardroom and phone booths. Approvals: DMCC fit-out approval and Civil Defence.

Related service: Office fit-outFAQ

This case study shows how HAO Contracting would deliver this property. Images are visualisations of the works in progress and the finished result, prepared for the proposal.

Room by room

Reception & arrival

Scope
  • Oak-slat backdrop with LED wash
  • 3.2 m reception desk – Calacatta-look top, fluted oak front
  • Frameless glass wall and double door into the open office

Open-plan workspace

Scope
  • Bench desks at 1.6 m per person, 1.4 m aisles
  • Desk clusters run towards the glazing for daylight
  • Carpet tiles, linear LED, concealed sprinklers

CEO office

Scope
  • Executive desk by the glazing, facing the room
  • Full-height oak joinery wall with integrated LED
  • Lounge corner for informal meetings

Boardroom – 14 seats

Scope
  • 5 m oak table parallel to the window wall
  • Oak veneer AV wall with 86" screen and video-call camera
  • Acoustic ceiling and dimmable lighting

Team area & manager office

Scope
  • Glass-fronted manager office against the window
  • Two clusters of four bench desks
  • Two acoustic phone booths

Co-working café – 20 seats

Scope
  • 3 m staff coffee bar with fluted oak front and stone top
  • 3.6 m communal work table with power in the top
  • Window laptop counter and booth seats
Materials

Natural oak veneer · Calacatta-look stone and porcelain · warm-grey carpet tiles · frameless glass with matt-black frames · brushed brass and matt black · bouclé and charcoal fabric · concealed sprinklers to UAE Fire Code

Programme

From handover to move-in in 18–24 weeks

1

Design & approvals

3–4 weeks

Layout, MEP design, landlord, DCD and authority approvals

2

Procurement

4–6 weeks

Joinery, glass, stone and furniture – factory-direct where it pays

3

Fit-out works

10–12 weeks

Ceilings, partitions, MEP incl. sprinklers, finishes, joinery and AV

4

Snagging & handover

1–2 weeks

Testing, Civil Defence inspection and completion certificate